# RACI And Sprint Plan

Дата: 2026-05-21  
Scope: operating model for launching ErgoCommunity.org as a community-run contribution hub.

## Required Owners Before Public Launch

| Role | Accountable For | Launch Gate |
| --- | --- | --- |
| Portal Lead | Scope, priorities, release decision | Go / No-Go / Preview |
| Safety Reviewer | Sensitive links, reports, risk states | No high-risk link published without review |
| Project Reviewer | Project cards, owner confirmation, stale states | 20 project cards reviewed |
| Weekly Pulse Editor | Weekly routing engine and contributor recognition | Pulse #1 ready |
| Technical Maintainer | Site quality, deploy, QA defects | Launch QA pass |

Use real names or handles before publishing. Placeholder roles are not enough for launch.

## Current Owner State

| Role | Current State | Launch Impact |
| --- | --- | --- |
| Portal Lead | Placeholder only | Blocks full launch |
| Safety Reviewer | Placeholder only | Blocks high-risk links |
| Project Reviewer | Placeholder only | Blocks project confirmation |
| Weekly Pulse Editor | Placeholder only | Blocks public Pulse broadcast |
| Technical Maintainer | Placeholder only | Blocks production deployment sign-off |

Limited preview can continue while these roles are placeholders if the preview label and safety gates remain visible.

## RACI Matrix

| Workstream | Responsible | Accountable | Consulted | Informed |
| --- | --- | --- | --- | --- |
| Role paths | Portal Lead | Portal Lead | Editors, local leads | Community |
| Work board | Editors | Portal Lead | Project reviewers | Contributors |
| Project cards | Project Reviewer | Portal Lead | Maintainers, safety reviewer | Community |
| Verified links | Safety Reviewer | Portal Lead | Technical maintainer | Community |
| Weekly Pulse | Pulse Editor | Portal Lead | Project reviewers, safety reviewer | Subscribers |
| Creator kits | Campaign Reviewer | Portal Lead | Safety reviewer, local leads | Creators |
| Governance Watch | Governance Reviewer | Portal Lead | Forum participants | Community |
| Launch QA | Technical Maintainer | Portal Lead | Editors | Community |

## Two-Week Sprint Cadence

### Monday

- Backlog triage.
- Stale task review.
- Project owner follow-ups.
- Safety report triage.

### Wednesday

- Content review.
- Safety review.
- Project card verification.
- Governance summary review.

### Friday

- Weekly Pulse publication.
- Contributor spotlight.
- Demo/retro.
- Next priority slot selection.

## Sprint 1 Goal

Launchable MVP operating slice.

## Sprint 1 Backlog

### P0

1. Assign real owners for the five launch roles.
2. Finalize 20 seed tasks with owner, source, proof, review date and status.
3. Finalize 20 project cards with contact, source, risk state and verification state.
4. Prepare Weekly Pulse #1.
5. Review all wallet, bridge, DeFi and support links.
6. Publish official-vs-community explainer.
7. Complete launch QA pass.

### P1

1. Prepare first creator kit.
2. Prepare first local cell starter kit.
3. Create contributor spotlight receipt.
4. Draft governance risk/rollback template.

### P2

1. GitHub issue import pilot.
2. Forum highlight automation.
3. Events calendar.
4. Contributor profiles.

## Launch Decision

### Go

- All P0 gates closed.
- No high-risk links unresolved.
- Pulse #1 ready.
- Owner names assigned.

### Limited Preview

- One P0 gate open, but no safety-critical issue.
- Published with visible preview label.
- Feedback window and owner assigned.

### No-Go

- Sensitive links lack safety review.
- Official/community boundary unclear.
- Work board lacks owners or proof requirements.
- Project cards lack freshness or risk state.